Farm Book, page 37
by Thomas Jefferson
by Thomas Jefferson
Rates of estimating builder's work.
s | d | ||
Framing is from 7/6 to 15/ the square of 100. sq. f. according to the quality from the slightest to the strongest, & if found provisions etc. 1/3 is to be deducted. call 1. square then | 0 | 15 | 0 |
sawing the stuff (about 50. f.) | 0 | 3 | 0 |
133. do. of feather edge plank. (it laps 2.I. & shews 6.I.) | 0 | 8 | 0 |
planing & putting up | 0 | 7 | 6 |
100. 20d. nails | 0 | 1 | 9 |
100. square feet of lathing @ 3d. 1/2 the square yard | 0 | 3 | 3 |
450. 4 d . nails | 0 | 3 | 9 |
2. | 02. | 3 | |
painting 3. coats of white lead, paint & oil included | |||
The same work done in brick of 1 1/2 bricks thick would take 1800. bricks, worth, making, laying, finding etc. @ 40/ | 3 | 12 | 0 |
The same done in stone would take 6 perch (18. I. thick) the laying of which is worth | 0 | 15 | 0 |